ARCO National Construction partnered with Hines to develop Chelsea Point, a 146,409-square-foot speculative freight-forwarding facility at 250 Marginal Street in Chelsea, Massachusetts. The facility includes a 36-foot clear height, 36 dock positions, a 2,000-square-foot office, 202 parking spaces, and a 3,000-amp electrical service.

The urban brownfield site presented overlapping environmental, civil, structural, and logistical challenges. ARCO coordinated the owner’s environmental, civil, and architectural consultants so site decisions could be evaluated together and advanced in compliance with project requirements.

Managing Brownfield Conditions

ARCO incorporated the project’s RAM and Soil Management Plan into its sitework planning and coordinated excavation, stockpiling, testing, and export. Unsuitable soils required the export of approximately 8,000 cubic yards of contaminated material with different classifications and disposal requirements.

The team sequenced cut-and-fill activities, separated and labeled stockpiles, coordinated testing and retesting, and worked with the owner’s environmental consultant to obtain landfill approvals. This integrated soil management with grading, utilities, access, and foundation work on a constrained urban site.

Engineering Around Subsurface Conditions

Demolition revealed a complex network of buried materials and utilities, including old piles, debris, duct banks, and unmarked lines. ARCO verified conditions in the field, coordinated design updates, and managed extensive water removal so construction could continue safely and efficiently.

To create a stable foundation across the site, ARCO used ground improvements beneath the building and retaining wall. A new cast-in-place retaining wall addressed a roughly 20-foot grade change at the northwest corner and supported the precast building system above it.

Value Engineering Through Early Coordination

ARCO worked with Hines throughout design and budgeting to find practical ways to improve value without changing the facility’s purpose or performance. The team looked for opportunities to simplify the building, coordinate structural and architectural systems, right-size equipment, and streamline utility routing.

One accepted solution replaced the planned PVC roof membrane with a 60-mil TPO system while maintaining the specified insulation and performance. This early review helped Hines make informed decisions that balanced cost, constructability, and long-term facility needs.

Delivering Ahead of Schedule

On an urban brownfield site, ARCO kept the schedule moving by coordinating consultant input, verifying underground conditions, and sequencing soil export, dewatering, utilities, and ground improvements. That coordinated approach helped Hines complete the high-capacity freight-forwarding facility ahead of schedule while addressing the site’s environmental and operational requirements.

ABOUT ARCO NATIONAL CONSTRUCTION

ARCO National Construction’s New England team brings regional expertise in industrial facilities, site development, value engineering, and complex brownfield construction. Through early coordination and disciplined execution, the team helps owners navigate local site and permitting requirements, manage risk, improve cost certainty, and create facilities that support long-term business needs.