ARCO Completes Phase 1 at ColdPoint Logistics

ARCO Completes Phase 1 at ColdPoint Logistics

ARCO Completes Phase 1 at ColdPoint Logistics.


Construction recently completed on a new 161,000 SF Freezer/Cold Dock Distribution Facility. The project specifications include:

34,000 SF Cold Dock
113,000 SF, -10o Freezer
5,200 SF Mechanical Room
8,400 SF Office
Three Blast Cells each with 48 Pallet Capacity Freeze from 38 oF to -5o F in 24 Hours
Railroad Spur Servicing the Building
Insulated Tilt-Up Concrete Exterior
Insulated Metal Panel Exterior for Expansion Walls
36’ Clear Height in Freezer
Ammonia Refrigeration System
Two-Story Office, 4,300 SF Each Level

To see more pictures from this project follow the link below

ColdPoint Logistics

ARCO Completes Another Facility for Quality Custom Distribution

ARCO Completes Facility for Quality Custom Distribution in Aurora, CO.


Construction recently completed on a new 69,000 SF cold storage tenant improvement project. The project specifications include:

26,000 SF Freezer
13,000 SF Cooler/Future Freezer
30,000 SF Cold Dock
33’ Clear Freezer and Cooler Height
Freon Refrigeration System
6” Reinforced Concrete Floor Slab
Dry Pendent ESFR System
LED Lights

To see more pictures from this project follow the link below

Quality Custom Distribution – Aurora, CO